- Submit membership application
- Submit new construction application
- Construction specs
- Provide document, page or volume number to land deed
- Schedule appointment with our staking team
- Email info/ contact info
- Route of line is established, right of way easement is signed, and cost of construction is relayed
- Submit all paperwork with construction payment
- Allow approximately 30 working days for completion
- Powerline is built!
- Meter loops available for purchase If Meter loop is purchased though the Co-op, it will be installed along with any/all construction.
- Service is left hot with main disconnect OFF
HOTEC Meter Loops:
- Temporary services
- Contractor/builder is responsible for providing temporary service pole
- Service will be left hot with main disconnect OFF